Hello,
I have problem with making a simulation.
I have got a message: One or more of the NORMAL tasks are unchecked in the task selection panel when performing a (re)start.
I use robot YuMi with options: multimove coordinated and also conveyor tracking.
I added task for conveyor to robot controller and activated mechanical unit CNV.
I want only make a program using only one hand of robot, the rest (left robot hand and conveyor have no program).
In the simulation setup I make simulation only for that hand I set.
I have no idea how to fix it or what I doing wrong.
I would be grateful for any help.
I have problem with making a simulation.
I have got a message: One or more of the NORMAL tasks are unchecked in the task selection panel when performing a (re)start.
I use robot YuMi with options: multimove coordinated and also conveyor tracking.
I added task for conveyor to robot controller and activated mechanical unit CNV.
I want only make a program using only one hand of robot, the rest (left robot hand and conveyor have no program).
In the simulation setup I make simulation only for that hand I set.
I have no idea how to fix it or what I doing wrong.
I would be grateful for any help.
0
Best Answer
-
Not exactly sure what your issue is but I will make a guess. If the controller wants to have tasks for the other hand and conveyor, which you don't need. Make Dummy tasks for them which simply do nothing. WaitUntil FALSE; is an infinite wait, but those tasks will still be executing.Lee Justice5
Categories
- All Categories
- 5.4K RobotStudio
- 384 UpFeed
- 15 Tutorials
- 12 RobotApps
- 290 PowerPacs
- 405 RobotStudio S4
- 1.8K Developer Tools
- 241 ScreenMaker
- 2.7K Robot Controller
- 282 IRC5
- 44 OmniCore
- 6 RCS (Realistic Controller Simulation)
- 3 RobotStudio AR Viewer
- 746 RAPID Programming
- 15 Wizard Easy Programming
- 110 Collaborative Robots
- 3 Job listings