Synchronize to RAPID on old station, save the module out, load module to new virtual controller, synchronize to station.
5 -
Multiple modules in the virtual controller is okay but not with the same name or same named data -- it will save over modules, procedures, and program data (targets, work objects, etc.) that have the same name when you synchronize to RAPID. If you want to keep the previous data, it's easiest to right-click and save the module out of RobotStudio rather than renaming everything every time you synchronize to RAPID.
Post edited by soup on1
Answers
-
It worked. Thank you very much.Can I have two modules in one station ? Because I had to replace the (empty) module while loading the old module (with required target points and paths)0
Categories
- All Categories
- 5.5K RobotStudio
- 393 UpFeed
- 18 Tutorials
- 13 RobotApps
- 297 PowerPacs
- 405 RobotStudio S4
- 1.8K Developer Tools
- 249 ScreenMaker
- 2.7K Robot Controller
- 309 IRC5
- 59 OmniCore
- 7 RCS (Realistic Controller Simulation)
- 783 RAPID Programming
- AppStudio
- 3 RobotStudio AR Viewer
- 18 Wizard Easy Programming
- 105 Collaborative Robots
- 4 Job listings