PickMaster5 project modification via backup file (and restore)
Hi,
I wonder if it's possible to modify PM5 project via backup:
1) Get a current backup from the controller
2) Retrieve PM5 project from the backup
3) Modify PM5 project in PickMaster program
4) Replace the PM5 project in the backup
5) Restore backup in the controller
The reason I'm asking is that I am trying to save travel time to customer. If the customer can give the latest backup so I can modify it at the office and they restore the backup that already has the modified PM5 project, that would be brilliant!
Thanks for all the answers.
I wonder if it's possible to modify PM5 project via backup:
1) Get a current backup from the controller
2) Retrieve PM5 project from the backup
3) Modify PM5 project in PickMaster program
4) Replace the PM5 project in the backup
5) Restore backup in the controller
The reason I'm asking is that I am trying to save travel time to customer. If the customer can give the latest backup so I can modify it at the office and they restore the backup that already has the modified PM5 project, that would be brilliant!
Thanks for all the answers.
Tagged:
0
Categories
- All Categories
- 5.5K RobotStudio
- 396 UpFeed
- 18 Tutorials
- 13 RobotApps
- 297 PowerPacs
- 405 RobotStudio S4
- 1.8K Developer Tools
- 250 ScreenMaker
- 2.8K Robot Controller
- 312 IRC5
- 59 OmniCore
- 7 RCS (Realistic Controller Simulation)
- 793 RAPID Programming
- AppStudio
- 3 RobotStudio AR Viewer
- 18 Wizard Easy Programming
- 105 Collaborative Robots
- 5 Job listings