I have created a station and controller with the multitasking option enabled. I have four tasks I am attempting to synchronize to station, but only T_ROB1 synchronizes and I get the following warning: Task exists in controller but not in station [3].
Does anyone know a fix for this?
Thank you.
Does anyone know a fix for this?
Thank you.
Tagged:
0
Answers
-
RESOLVED: Since the tasks were non motion tasks, they don't need to be in the station to run.1